Contract Duration: 12 Months
Responsibilities:
End client requirements:
Overview of Requirements:
- Execute the Scope of Work for Turbine Generator and Main Turbine Valves during Outage U1RF02
- Complete Maintenance Services for TG Components, including but not limited to Pre-Planning and Project Management – 1 month before the Outage Starts Mobilization Tasks – 2 weeks before Outage starts
GENERATOR Activities – 10 days from Clearance is hung and Work Permit is Released.
- VPLT Stator Bars Dry and Test (Vacuum/Pressure test) – 8 days from the clearance is hung and
- Work Permit is released.
- VALVE Maintenance (2 MSs and 2 CVs) – 10 days from the clearance is hung and Work Permit is released.
- Demobilization – 1 week after Valve work is completed
Project Management Closure – 1 week after the last activity is completed.
Profile:
- Turbine-valve technical knowledge
- Power plant experience
- Fluent English